Hello,guys

Today I meet two questions:

1. When I want to make 2d verification. But sometimes it doen not show buttom of 2d verification. Why?

2. I use 5 axis mill operation (veriable contour).Then I select part as workpiece geometry. When I generated. Tool path is confused. then change to MCS as workpiece geometry. It is ok. Why?

 

Thanks!

 

-----------------------------------------
NX3.0
NX6.0
NX10.0.35
NX11.0.1
UG_NX is my favorite !!!!!!
2 REPLIES

Re: 2d verification and 5 axis confused tool path

This is the forum to ask for help with NXOpen programming, your question is best suited for the NX manufacturing forum Smiley Wink

Stefan Pendl, Systemmanager CAx, HAIDLMAIR GmbH
Production: NX10.0.3, VERICUT 8.0, FBM, MRL 3.1.4 | TcUA 10.1 MP7 Patch 0 (10.1.7.0) | TcVis 10.1
Development: VB.NET, Tcl/Tk    Testing: NX11.0 EAP, NX12.0 EAP

How to Get the Most from Your Signature in the Community

Re: 2d verification and 5 axis confused tool path

To get the best response, please post these as 2 separate topics in the Manufacturing Forum