Hi, 

 

I'm working on a simulation of a worker to carry the part away after processing 25 parts. The operator is required to carry all the 25 part to the next process. Is it possible to simulate such process? I'm thinking of writing a method script for the control tab - exit but I'm not too sure if it is an ideal method to do so. If it is an ideal method to simulate the process, how do I write up the script? hope to get some responses and help soon. Thanks in advance.

6 REPLIES

Re: A worker carry multiple parts

Pioneer
Pioneer

Hi Sri, 

 

Yes, you could do in a different way by using a transporter (as human). Check the attached rough model. 

 

Regards,

Sundara 

Re: A worker carry multiple parts

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

look here

 

https://community.plm.automation.siemens.com/t5/Plant-Simulation-Forum/Worker-moving-multiple-Parts/...

 

you can set the capacity of the worker to 25 and define a max. waiting time in the exit strategy (>25x procTime of the station), so that the worker is waiting for 25 parts

--> read the help for exit strategy: carry part away

Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: A worker carry multiple parts

Creator
Creator
Thank you Sundara, but can you share with me how did you get the transferstation model? I'm very interested in trying it out and at the same time, if I were to set the transporter as a human, I will not be able to set the transporter as an importer to the particular process right?

Re: A worker carry multiple parts

Creator
Creator
Hi Steffen, I am not able to open the model that you have shared before. I'm using version 14. could you share with me the model in version 14? I will be truly grateful if you could help me out with this. Thank you

Re: A worker carry multiple parts

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

here you can download the example

 

https://www.bangsow.eu/detail_en.php?id=732

 

it is done with version 12, you should be able to open it with version 14

Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: A worker carry multiple parts

Pioneer
Pioneer

Hi Steffen, 

 

Thank you for your comments. 

 

I have one question and Please see my query in the below link 

 

https://community.plm.automation.siemens.com/t5/Plant-Simulation-Forum/To-carry-parts-from-2-buffers...

 

It would be really helpful if you assist me in this. 

 

Thanks!