EntranceCtrl Before Actions not working with Workers

Solution Partner Genius Solution Partner Genius
Solution Partner Genius

Hello,

 

I am trying to wait a little while before calling a worker to process a station, but the worker is called directly and the entrance control "before actions" is ignored.

 

The tooltip for "before actions" says the method is executed before any services are requested through the importers.

 

Is my attached model functioning by design? How do I make it so the worker isn't called to the station for processing before something else happens?

 

I'm running Plant Simulation 13.0.2

 

Thank you.

2 REPLIES

Re: EntranceCtrl Before Actions not working with Workers

Siemens Legend Siemens Legend
Siemens Legend

Hello,

 

A wait statement in the entrance control with "BeforeAction" is not supported.

 

But you can use the importer request control. Here a wait before starting the import is possible.

 

Kind regards

Karola

Re: EntranceCtrl Before Actions not working with Workers

Solution Partner Genius Solution Partner Genius
Solution Partner Genius
Thank you, this worked as expected.