Re: (HELP) one process with two different entities and go to different process afterwards

Pioneer
Pioneer

Thank you so much!

 

Blanket will go to CoolingDown process and for Linen goes to Checking process. and when folding and checking process is started, they will be processed one by one, not as whole batch or group...

Highlighted

Re: (HELP) one process with two different entities and go to different process afterwards

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

the exit behavior is ok

two issues:

- don't use the cycle time: 20 minute cycle time means: each 20 minute can enter one MU the station, you need to set the processing time if the process should last 20 minutes

- your buffer capacity was 0, this blocks the flow

 

 

Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: (HELP) one process with two different entities and go to different process afterwards

Pioneer
Pioneer

Okay!!

 

Yes, I forgot to input them. Thank you very much (again), Steffen!!