Hi everyone.
I want to make a pause time every 1.5 days.
However, Shift calendar can only set the pause time within 24 hours.
How do I create this?

4 REPLIES

Betreff: Pause in shift calendar

Hi SubinChae,

you can start and end a pause using simtalk. First methodcall comes from init-method when simulations starts. Then call the method again every 1.5 days.

regards dst

simple++ / eM-Plant / Plant Simulation

Betreff: Pause in shift calendar

Thank you dst
I'll try it.

Betreff: Pause in shift calendar

The attached model for Plant Simulation 12.0 shows, how you can solve it without SimTalk. For this purpose there is the object Generator.

Betreff: Pause in shift calendar

Thank you for your reply.