Reverse simulation

Valued Contributor
Valued Contributor

Gentlemen, Good afternoon.
Is there any way to create a reverse simulation in PlantSimulation?
I'll try to explain better: I own a date for the delivery of a product, and would like to create a schedule to tell me when I need to start production for the process to end on that date.
I even thought about something simulate the date that I have back, but EventController need to tell the time back as well.

Any suggestions on this?

3 REPLIES

Re: Reverse simulation

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor
the shiftCalendar provides a method for backward scheduling see:
shiftCalendar.schedule
Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: Reverse simulation

Valued Contributor
Valued Contributor
How does this method?
I call it in the Init?

Re: Reverse simulation

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor
"How does this method?"
look in the help!

I call it in the Init?
You can call it in the init or in the reset method. You could calculate the creation dates for the MUs (source - delivery list) based on the scheduled finish dates and the sum of production times + waiting and transport times.
Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net