Hi all,

 

Is it possible to run multiple frames at the same time? Such that I can save time by running multiple frames at night.

 

Regards,

 

William

2 REPLIES

Re: Running multiple frames simultaneously

Siemens Phenom Siemens Phenom
Siemens Phenom

Hi William,

 

you can have only one running Event Controller in your model.

 

But you can start as many Plant Simulation processes as you like.

This way you can run multiple simulations in parallel.

 

Regards,

Ralf

Regards,

Ralf
------------------------------------------------------------------------------------------------------
Did you like the answer? Then click the Thumbs Up button.
Did the answer solve your problem? Then accept the answer as solution.

Re: Running multiple frames simultaneously

Pioneer
Pioneer

Thanks Ralf, same result!