Hi!

I am creating a simulation model where I want my machines (or at least some of them) to stop working during the weekend. My Shift Calendar contains of two shifts (06.00-14:00 mon-fri, 14:00-22.00, mon-fri), and I have inserted all my machines (SingleProcs) into "Resources" of the ShiftCalendar. Do I need to use some kind of method to make the machines stop during the weekend, or is this enough?

Best Regards

Sofi

1 REPLY 1

Re: Shift Calendar: stop machines during weekend

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

you need to select the shiftcalendar in the tab control or drag the singleProcs on the shiftCalendar. Plant Simulation  enters the assigned stations to the list ressources in the shiftcalendar (you dont need to do this).

 

At the weekend the stations should change to the state unplanned, this you will find also in the statistics tab of the  SingleProcs (and gray LED).