ShiftCalendar

Hallo;

 

I created one model but whenever I entered shift calendar and to connect with all Process and Buffer then I don't get a summary Report.

 

I need Help to solve this Problem.

 

 

4 REPLIES 4

Re: ShiftCalendar

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

you need to set an end in the eventController; if the eventController reached the end, the summary report will be displayed

Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: ShiftCalendar

Hallo Sie

 

can you suggest me How event controller reached the end?

 

Because without Shift Calendar it works

 

I want to know how it works in This Model

 

 

Re: ShiftCalendar

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor

eventController - tab settings - set a end in the field end (I have set it to one day)

 

 

Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: ShiftCalendar

Gears Phenom Gears Phenom
Gears Phenom

@Manish_Togadiya  schrieb:

without Shift Calendar it works


Just to add an explanation to Steffens solution: your model without shiftcalendar runs out of events to process after the 100 MUs have been produced.

If you activate the shiftcalendar, the shift calendar will endlessly schedule more breaks and shifts (which are also events), so your model never stops (unless you set a defined end time like Steffen described).

___________________________________________________________
Alex Dilg, Consultant at SimPlan AG (www.SimPlan.de)
This post was good and/or helpful to you? Please provide some Kudos, thank you!