Hallo

 

I want to make a schedule for a week in Plant Simulation

In my model is four different Entity and I want to work on Object Red And Blue from Monday to Wednesday and similarly Yellow and Black Objects from Thursday to Saturday.

I tried with Trigger but I don't know its possible with trigger 

also, I need to give the End in Event controller

 

I also want to know

How works Trigger?

1 REPLY 1

Re: Trigger

Phenom
Phenom

there was a similiar request (based on a monthly level) in this forum some time:

 

https://community.plm.automation.siemens.com/t5/Plant-Simulation-Forum/Monatliches-Anlieferregime/m-...

 

This could be modified to ( your) weekly level request

 

Anyway, please find attached the trigger solution.

 

For the created sequence, have a look in the creationTable ( Source statistics tab)

 

Unbenannt.PNG