Worker take 2 or more parts

Experimenter
Experimenter

Hello I want to simulate a worker that takes 2 parts from a buffer and carries them to another part of the factory. I assign a capacity of two to the worker but it continues take only 1 part. What can I do in order to the fact that the worker takes 2 parts?

 

3 REPLIES

Re: Worker take 2 or more parts

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor
you need to set a dwell time (e.g. 10 seconds) in the tab exit Strategy (carry part away).. Then the worker will wait this time for the requested number of parts.
Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu
mail: steffen@bangsow.net

Re: Worker take 2 or more parts

Experimenter
Experimenter
And how I establish the number of parts the worker has to take?

Re: Worker take 2 or more parts

Gears Esteemed Contributor Gears Esteemed Contributor
Gears Esteemed Contributor
you need to set it as the capacity of the worker; the dwell time needs to be long enough to collect these number of parts
Steffen Bangsow
freelance simulation specialist  
web: www.bangsow.eu