Define new participants for a Change in TC11

In change management there is an ANALYST  participant defined. A change can have only 1 ANALYST. In my case I have to split up the ANALYST in 3-4 groups:

  • Engineering
  • MFG
  • Quality
  • etc

In BMIDE I can define new Participants, but I want them only for an ECR.

Is this handled by preferences or in BMIDE and how? 

 

Regards,

 

Menk Slot

2 REPLIES
Solution
Solution
Accepted by topic author Menk
‎05-29-2017 04:48 AM

Re: Define new participants for a Change in TC11

You can configure  business objects constants -ParticipantUsedOnObjectTypes  on Participant business object to define set of objects to which this participant is applicable.

Re: Define new participants for a Change in TC11

Hi Rajesh,

 

Thanks for the information. 

 

Regards,

 

Menk