Revision Update.

Valued Contributor
Valued Contributor

Hi.

 

When I revise a part and then open it in ST7, it is not linked to the newly revised model.

When I go to edit link and change source, it doesn't work.

 

I have to close the draft down, oupen the model, close the model down.

When I then re-open the draft the link is ok.

 

How can I make sure the draft and model are linked when I revise the part in teamcenter?

4 REPLIES

Re: Revision Update.

If you are using Solid Edge, you shouldn't revise from TC. SEEC keeps all those links in place but TC doesn't do it well. Use Structure Editor or SE to make your revision and the links will be fine.

 

Jamie

Re: Revision Update.

Experimenter
Experimenter
@jamie, When we revised in TC, we are getting option to carry forward other related non cad documents in that particular revision, on the other hand In SEEC editor this option is not available.

Re: Revision Update.

Correct, in SEEC you don't get those options. But you can work on your deep copy rules to apply general rules each time you make a revision. If you are already going into TC to modify what is attached to the new revision each time, then I'd suggest do those actions after you make the revision in SEEC.

Re: Revision Update.

Valued Contributor
Valued Contributor

Hi Everyone.

 

Hope you had a good break.

 

When I revise my drawing to REV 'A'.  for some reason the date of the original revision changes to present day.

It does this if I up rev in teamcenter and in SE.

 

Why is this?

This is in my callout: %{Created/@d/M/yy}